Public consultation: Register for Monday, 6 October 2025
The project

The Ravenscraig AI Energy Campus will combine a state-of-the-art AI data centre campus with an on-site Battery Energy Storage System (BESS).

Located on land to the east and west of the Ravenscraig masterplan, the development will connect directly to high-capacity substations at Wishaw and Newarthill, positioning it perfectly to meet Scotland’s growing demand for secure data capacity and clean energy storage. 

We are proposing a 550MW green AI data campus alongside a 650MW BESS, designed to deliver critical digital services while supporting Scotland’s Net Zero and regeneration ambitions.

Purpose-built to the highest technical, environmental, and safety standards, the campus will:

  • Store renewable energy and deliver it instantly when required (the BESS will be consented via the Scottish Government’s Energy Consents Unit (ECU) through a Section 36 application).
  • Ensure uninterrupted, ultra-low latency service.
  • Provide 24/7 operational resilience, even during fluctuations in the wider electricity network.

By integrating advanced digital capability with large-scale energy storage, the Ravenscraig AI Energy Campus will be a cornerstone of Scotland’s clean energy future and a catalyst for local regeneration.

The data centre illustrative site masterplan

The Ravenscraig campus is split across two areas, east and west, each with its own masterplan. The eastern site is larger and accommodates six data halls, while the smaller western plots host three buildings integrated into the local road network.

The eastern site 
The western site 

Why this site has been chosen

Ravenscraig Updated

Strategic location

Ravenscraig offers a rare combination of space, infrastructure, and regeneration opportunity that makes it ideally suited for a development of national significance.

Image of a transformer

Grid resilience

The site has direct access to a high-capacity dual grid connection from the nearby Newarthill and Wishaw substations, providing the level of power resilience essential for data centre operations.

Image of Scottish Parliment

Policy alignment

The proposals support both national and local priorities, including Scotland’s Net Zero targets, ambitions for advanced digital infrastructure, and inclusive economic growth.

Timeline

The following timeline outlines the key milestones for the proposed development, from initial grid connection agreements to operation.

While these dates are estimates and subject to change, they provide an overview of the project's journey and the steps required to bring it to life. We are committed to keeping the community informed as the project progresses.

Q2 – 2025
Grid offer accepted
AdobeStock_448626984

In June 2025, we secured a formal agreement with the electricity network operator NESO, confirming that the project can connect to the grid. 

Q3 + Q4 2025
Site surveys
Image of a survey

In parallel with the public consultations, specialist consultants will carry out detailed environmental, technical, and ground condition surveys.

Q3 2025
Public consultations
Image of a public consultation

This is where we meet with local residents, community groups, and stakeholders to share plans, answer questions, and gather feedback. This input is helping shape the final design and ensures local voices are heard.

Q4 2025
Submit planning application
Image of a pen and paper

We submit a formal planning application to the relevant authorities, including all technical studies, community feedback, and environmental assessments.

Q1 2026
Planning decision
Image of a meeting

The planning authority reviews the application, considers public comments, and makes a decision on whether the project can go ahead.

Q2 2026
Preparing for construction
Image of a hard hat on table

We will liaise with local councils, skills providers, and community partners to explore opportunities for local employment, training, and supply chain involvement.

2026
Construction starts
Image of man in hard hat

If approved, work begins on preparing the site, installing equipment, and building any necessary infrastructure, such as access roads or cabling.

2028
Construction complete
Image of a data centre interior

The build finishes, and we begin a testing phase to make sure everything works as designed, meets safety standards, and is ready for operation.

2029
Operation starts
AdobeStock_1573071637

The AI Data Campus becomes fully operational, providing secure, high-capacity digital infrastructure with a focus on renewables.

We value your opinions, please take part in our feedback survey

It only takes two minutes, and your answers could make a meaningful difference to the project.